May 22nd update from Town Manager, Jeff Jones:
Here is a latest update on the Clarksville Downtown Paving Project being performed by The Virginia Department of Transportation (VDOT).
Paving of the downtown area from the bridge to Seventh Street is complete. Downtown Virginia Avenue streets and parking are open.
The preparation of the section of the causeway on the area of the bridge from (Uppy’s – SUNOCO) to the business 58 bridge will continue on Thursday May 23 between 8 a.m. & 5 p.m. with tentative plans to pave this entire area after the Memorial Day Holiday on Tuesday May 28th between 8 a.m. and 5 p.m. There will be a combination of one lane remaining open with flaggers directing traffic in the morning hours with a full detour of the bridge to follow.
No work is scheduled to be performed on Friday May 24 and all roads will be open.
The painting of the street lines and parking area lines will be scheduled after the Memorial Day Holiday and are anticipated to be in the evening hours.
Thanks in advance for all your cooperation.